Council Works Update

Council works and projects update as at 1 April 2026:

Men’s Shed – Project has progressed int the Procurement Phase.

Madison Lyden Park Amenities – Contract has been awarded to the successful Contractor and work will commence onsite in April 2026.

Pearl Court Road Reconstruction – Road Reconstruction and drainage improvements works are underway. Although some unforeseen subgrade issues have been encountered the works are expected to be completed in early April 2026.

Allambie Road, Orielton – Road seal has been undertaken by the Contractor. Other remedial works commence in March and are expected to be complete in April 2026.

Shark Point Road Reconstruction – Work onsite is progressing and are expected to be complete in late April 2026.

Penna Road Reconstruction – Stormwater works are complete. Kerb, footpath and road reconstruction works are expected to be complete in mid-May 2026, subject to weather.

2025-26 Road Re-Seal Program – All road re-seal works across the municipality are now complete.

Tasman Highway Footpath Renewal – Footpath renewal works along Tasman Highway; northern side between Arthur Street and Devenish Drive and southern side, west of Attunga Drive are mostly complete. Minor works to utility services are outstanding pending the availability of specialist contractors.

Gatehouse Drive & Weston Hill Road Footpath – New footpath and kerb along the northern side of Gatehouse Drive and reconstruction of the existing footpath along the western side of Weston Hill Road works have commenced onsite and are expected to be complete by April 2026.

Franklin Street, Dunalley – Road reconstruction and drainage improvement works will commence onsite in April 2026. Expected completion is May 2026.

Flyway Park Pump Track, Midway Point – Contract has been awarded to the successful Contractor for the design and construction of a Pump Track, design work will commence in early April 2026 with work onsite commencing in late April 2026.