Council Works Update

Council works and projects update as at 1 June 2026:

Men’s Shed – Works have commenced the Men’s shed infrastructure outside the building footprint, with the installation of stormwater drainage and electrical conduit to the site. Materials have been imported to level the site for the new building. The Procurement process has been undertaken, and engagement of the successful Contractor is currently underway.

Madison Lyden Park Amenities – Power supply, concrete slab and under slab drainage is complete. Structural steel frame has been erected and cladding is about to commence. Completion is expected in mid-July 2026.

Shark Point Road Reconstruction – Roadworks were completed in April 2026, footpath works are expected to be completed in early June 2026, subject to weather.

Penna Road Reconstruction – Works are continuing and are expected to be complete by mid-June 2026, subject to weather.

Gatehouse Drive & Weston Hill Road Footpath – New footpath and kerb along the northern side of Gatehouse Drive and reconstruction of the existing footpath along the western side of Weston Hill Road works are continuing and expected to be complete by late June 2026.

Carlton River Rd between Dodges Hill Rd and Convoy Rd – Footpath renewal works have commenced and are expected to be completed by late June 2026.

Franklin Street, Dunalley – Footpath works are currently underway to connect the park at Imlay St to the Community Hall and the Servo at Bay St. Road base course on Franklin St will commence in early June with project completion expected in mid-June 2026.

Flyway Park Pump Track, Midway Point – Excavation work onsite has commenced. Weather permitting, completion is expected by late June 2026.