Works

COUNCIL WORKS UPDATE

Current and soon to be commenced Council works and projects as at 24 December 2022:

Pembroke Park Stadium – Electrical, plumbing, exterior cladding, plastering and window installation is complete. Internal fit out and joinery has commenced.

Pembroke Park Stadium car park and lighting – stage two works are ongoing.

White Hill Road – Resheeting has commenced on White Hill Road. Works will be carried out on the section from Musgrove Gate to the end of the Road, and will be ongoing for approximately two weeks. Trucks and trailers will be using the road during this time, so some delays can be expected.

Dodges Ferry Carlton Loop – The gravel footpath from Carlton Beach Surf Life Saving Club to Moomere Street is currently underway and scheduled for completion shortly. Renewal of the Moomere asphalt footpath will commence this month.

Kannah Street – Stormwater pits and pipes will be constructed once water levels recede.

Lewisham Road Stage 3 – Realignment of the road and construction of a box culvert bridge at ‘Fools Corner’ has commenced. Works are expected to be completed in March 2022.

Stormwater Grate Replacement – Damaged/rusted stormwater grates throughout the Municipality are being replaced.

Road Resheeting: Resheeting of Pawleeena Road will be completed in late January.

Bryant Street – Resealing of Bryant Street in Midway Point will be completed in late January.

Shark Point Road – Road reconstruction works have now commenced on Shark Point Road. From Penna Road west for approximately 1.3km, works will include pavement works and resealing and will take approx. 6 weeks to complete weather and other factors dependent. Some delays can be expected. Road users are reminded to please observe and obey roadside works signage, drive safely through the work site and watch out for road workers.

Recently completed works include:

Roadside Spraying – The Roadside Spraying program has been completed.

First Avenue and Jetty Road, Dodges Ferry – New footpath down the eastern side of First Avenue, and along the northern side of Jetty Road is complete.

Main Road, Sorell – Pedestrian refuge on Main Road, near Forcett Street is complete.

Pembroke Park Cricket Nets – Installation of two new cricket nets and extension of the existing nets is complete.

Attunga Drive, Sorell – Footpath renewal works are complete.

Pennington Drive/Dubs & Co/Station Lane – Construction of pedestrian refuges and kerb ramps is complete.

Road Works

Lewisham Road Stage 3

29 November 2021 - 25 March 2022

Realignment of the road and construction of a box culvert bridge at ‘Fools Corner’ has commenced.
Please observe all onsite works signage.
Works are expected to be completed in March 2022.

Facilities

Pembroke Park Stadium

21 July 2021 - 18 March 2022

CONSTRUCTION UPDATE AS OF DEC 2021: Electrical, plumbing, exterior cladding, plastering and window installation is complete. Internal fit out and joinery has commenced.
Council is committed to developing Pembroke Park as the premier sporting complex for the south east region.
The stadium complex will include two basketball courts, gym, offices, meeting room, function room, amenities, storage, canteen, parking, access and landscaping.
The construction tender for the stadium complex was awarded to VOS Construction.
Funding for the project was secured through grants of $2.5 million from the State Government and $6 million from the Federal Government’s Community Development Grants Programme.