Works

COUNCIL WORKS UPDATE

Council works and projects update as at 1 March 2024:

🚧 BMX Track @ South East Sports Complex – The perimeter fence is nearing completion. The installation of power supply is now complete. Track builders returned in early February and completed the installation of the track surface and linemarking.

🚧 Sorell Streetscape Stage 3 (Fitzroy Street to Somerville Street) works are nearing completion with Stage 4 in Cole Street (Gordon to Pelham) commencing shortly after.

🚧 Sorell Carriage Shed – Tasmanian Heritage have reviewed the documents have given an exemption for the proposed works. The design is being finalised and will soon go out for quotes.

🚧 Gate Five Road/Carlton Beach Road (Vulnerable Road User Program) – Details for land acquisition have been provided to the relevant parties and a formal agreement is being finalised.

🚧 Lewisham Scenic Drive (Gregory Street to Mary Street) – Footpath renewal works are nearing completion.

🚧 Tamarix Road (Nerine Street to Grebe Street) – The Contractor has commenced works on the southern side of Tamarix Road.

🚧 Marion Bay Road and Bay Road Reconstruction – Work have commenced, culverts have been installed and work on the road reconstruction is underway.

🚧 Bream Creek, Marion Bay Road Reconstruction – The tender has been awarded with an anticipated start date mid to late March 2024.

🚧 Primrose Sands Road and Grevillea Street Reconstruction – The tender has been awarded with an anticipated start date of late March 2024.

🚧 Road Reseal Program 2023-2024 – Works inclusive of asphalt overlays have been delayed and will be due to start in mid-March. The program is expected to take 4 weeks to complete.

🚧 Stormwater Culvert replacements – Culvert replacements approved as part of our Capital Works program are ongoing.

There are no current works.